Aberdeen Bio Hub

Aberdeen

About the project

Our most recent project for JB Construction, to revitalise their busy warehouse floor, showcasing our expertise in precision and quality commercial flooring solutions.


Our process began with meticulous concrete grinding and thorough vacuuming to prepare the surface.


After applying two coats of primer, we installed 10mm of Webber 4610, allowing it to settle for 24 hours before joint cutting to prevent cracking.


Following another 24-hour period, we polished the slab to a stunning 3000 grit finish, delivering a durable and visually appealing solution that exceeded the client's expectations.

Project details

About the project

Flooring solution

Micro Cement

Sector

Commercial

Year

2024

Our most recent project for JB Construction, to revitalise their busy warehouse floor, showcasing our expertise in precision and quality commercial flooring solutions.


Our process began with meticulous concrete grinding and thorough vacuuming to prepare the surface.


After applying two coats of primer, we installed 10mm of Webber 4610, allowing it to settle for 24 hours before joint cutting to prevent cracking.


Following another 24-hour period, we polished the slab to a stunning 3000 grit finish, delivering a durable and visually appealing solution that exceeded the client's expectations.